The BT Gosforth House project highlights the expertise FTS has in delivering complex refurbishment works in the North of England, under tight timelines, while ensuring uninterrupted client operations.
Tech Sector | 110,000 sq ft | Cat B | Value £6.8m | All levels | Duration 45 Weeks
HVAC
Data
Engineering
Sustainability
Building Performance
2,622
Installation of CAT 6 data points
Overhaul
19No air handling units ED-CD plug fans and DX coils to enable the removal of natural gas
Live Call Centre
Within 5No comms rooms during refurbishment works
Client testimonial
“FTS brought clarity to what was understandably a complex project. Dean and his team worked to fulfil our heavy data requirements through innovative MEP solutions combined with strong technical expertise to resolve some of the major stumbling blocks we had with our new campus.”
BT Gosforth
Client testimonial
“FTS brought clarity to what was understandably a complex project. Dean and his team worked to fulfil our heavy data requirements through innovative MEP solutions combined with strong technical expertise to resolve some of the major stumbling blocks we had with our new campus.”
BT Gosforth
Client testimonial
“FTS brought clarity to what was understandably a complex project. Dean and his team worked to fulfil our heavy data requirements through innovative MEP solutions combined with strong technical expertise to resolve some of the major stumbling blocks we had with our new campus.”
Whether you’re assessing an asset, planning a project or improving an existing building, our specialists can help define a strategy and deliver a solution for any issue you may be facing across sustainability, engineering or decarbonisation.
Talk to our team about how we can future-proof your development.